|
5 Year Capital Improvement Program (2007-2012)
Santa Maria
Blosser Basin -
Estimated Cost: $380,000
This project consists of constructing a pipeline to drain the Blosser
Basin. The Blosser Basin is currently drained and dried out by either
percolation through its earthen bottom or by pumping water out of the
Basin and into the Blosser Ditch, an earthen channel that takes drainage
towards the Santa Maria River. Water introduced into the Blosser Ditch
tends to promote vegetation that must be continually maintained. The constructed
pipeline will take water from the Basin to the Santa Maria River without
allowing the water to flow within the Blosser Ditch.
Bradley Channel
Improvements - Estimated Cost: $1,505,000
This project consists of improving two sections of the Bradley Flood Control
Channel in the City of Santa Maria. One section is approximately 1,750
linear feet of earthen channel located between Highway 101 and State Route
135 that will be lined with a concrete trapezoidal channel. The second
section is approximately 960 linear feet of earthen channel located between
East Donovan Road and Magellan Drive which will also be lined with a concrete
trapezoidal channel.
Each year, maintenance staff removes debris and sediment deposits from
the channel bottom and obstructive vegetation along the banks of the unlined
channels in order to maintain channel capacity and reduce flood hazards.
Completion of this project will reduce future maintenance costs and minimize
the flood hazard to adjacent properties.
Kovar Basin Expansion
- Estimated Cost: $1,575,000
This project consists of an expansion of the existing Kovar Basin, a storm
water detention facility, to provide greater storage capacity.
During extreme runoff events, existing storm water control facilities
located beyond the westerly urban limits of the City of Santa Maria tend
to become overwhelmed, thus leading to a breakout of uncontrolled flood
flows that traverse agricultural property.
Construction of this project will provide a greater volume of storm water
storage and thus minimize the frequency of the breakout of uncontrolled
storm water flows.
Santa Maria River
Levee Reinforcement - Estimated Cost: $21,425,000
This project will provide a secondary backup system to the Santa Maria
River Levee in case of levee failure. The first phase of this project
could consist of placing a sheetpile wall, or other alternative, the length
of the levee between Suey Crossing and US Highway 101, a distance of approximately
3,300 feet. This will provide flood protection to the adjacent neighborhoods
as well as the City of Santa Maria should the existing levee fail.
The Santa Maria River Levee was constructed by the US Army Corps of Engineers
between 1959 and completed in 1963. The Levee is now over 40 years old.
The Levee is 24 mile long and protects the City of Santa Maria as well
as thousands of acres of prime agricultural land from the Santa Maria
River. The Levee is constructed of sand with a rock rip rap facing. The
rip rap facing has degraded over the years to the point that it has reduced
effectiveness in withstanding the forces of the river.
Santa Maria River
Riparian Enhancement - Estimated Cost: $540,000
This project consists of planting willows along sections of the levee
that are vulnerable to river erosion, thus helping to protect the levee
while creating valuable riparian habitat. This is a cooperative project
between the Flood Control District, the Cachuma Resource Conservation
District and the National Fish and Wildlife Foundation administering the
grant funding which is part of the UNOCAL Guadalupe settlement. The project
will be done in phases extending over five years to be completed in June
2008.
Unit Two Channel
Improvements - Estimated Cost: $750,000
This project is intended to increase the hydraulic capacity of the Unit
2 (earthen lined) channel by realigning the channel to remove a sharp
S curve "kink" and widening approximately 5000 linear feet of
channel. The section of channel considered for widening varies in existing
bottom width of 8' to 12' and is preliminarily planned to be increased
to a bottom width of 16'. This project will require real property acquisition
from, and coordination with, adjacent farm land property owners.
Orcutt
Airport Ditch Lining
- Estimated Cost: $615,000
This project consists of replacing a portion of the earthen-lined trapezoidal
shaped Airport Ditch with concrete. The project is located along Skyway
Drive in Santa Maria. The ditch is subject to erosion and deposition in
downstream reaches that subsequently require cleaning. Lining a portion
of this ditch with concrete will minimize this on-going problem.
Mud Lakes Basin
Siphon Improvement - Estimated Cost: $880,000
This project will remove the 12" diameter (siphon) pipe outlet works
of the Mud Lake Basins and replace it with approximately 1300 linear feet
of new 18" (gravity draining) pipe. The existing outlet works operates
as a siphon, which requires manual priming of the system in order to drain
the basins. On occasion, maintenance crews have been unavailable to operate
the siphon system during storm events, resulting in the overtopping of
the basins. The new gravity draining outlet pipe will eliminate the need
to manually operate the siphon system.
RB7 Outlet Works
- Estimated Cost: $185,000
This project consists of acquiring permanent easements and constructing
a storm drain under Blosser Road south of Foster Road. The new storm drain
will be approximately 300 feet long and will discharge flow from a future
retention basin (RB7) to be built by the Santa Maria Airport District.
The existing drainage facilities are inadequate for the amount of stormwater
runoff received. During storm events, excess storm water runoff inundates
Blosser Road and adjacent properties. Construction of this culvert will
reduce flooding impacts.
Los Alamos
San Antonio Creek
Improvements - Estimated Cost: $1,470,000
This project consists of channel improvements along a portion of San Antonio
Creek in the community of Los Alamos. The current Federal Emergency Management
Agency floodmap shows a large portion of the developed properties subject
to flooding during a 100-year flood event. This project would provide
increased channel capacity and flood protection for the properties adjacent
to the creek, thus reducing the flood risks to these properties and regulatory
floodway limits.
Santa Ynez
Faraday Storm Drain
- Estimated Cost: $980,000
This project consists of acquiring easements and constructing approximately
1,920 feet of storm drain west of Faraday Street between Olive Street
and Pine Street in Santa Ynez. This neighborhood is in a low-lying area
between two existing drainage channels and currently experiences repeated
flooding during rain events. This storm drain will convey flood water
to Zanja de Cota Creek.
South Coast
Atascadero Creek
Lining Repair - Estimated Cost: $850,000
This project consists of constructing a 4 foot deep sheetpile cutoff wall
along the existing concrete slope lining on Atascadero Creek in Goleta.
The existing concrete slope lining was constructed in the mid 1960's to
protect adjacent residential subdivisions. Over the years, the channel
has degraded several feet exposing the bottom of the concrete slope liner.
Without any additional scour protection, the existing liner is subject
to failure during storm events. Sections of the liner have been damaged
and were reconstructed following the 1995 and 1998 winter storms.
Construction of this project is necessary to protect the existing concrete
slope lining and minimize future damage. This project will be funded by
South Coast Flood Zone benefit assessment revenues.
Las Vegas &
San Pedro Creeks at Calle Real - Estimated Cost: $8,110,000
This project consists of the construction of two improved reinforced concrete
box culverts (RCB). The first starts 300 feet east of Valdez Ave. along
San Pedro Creek, and crosses Calle Real, Highway (HWY) 101 and the Union
Pacific Railroad (UPRR). The second RCB starts east of Vega Dr. along
the Las Vegas Creek and crosses HWY 101 and the UPRR. During storm events,
Calle Real and HWY 101 are closed and numerous homes and businesses are
subject to flooding. The cleanup costs associated with the flooding in
past storm events are significant. Construction of these culverts will
greatly improve the capacity of the drainage system and reduce the flood
hazard to adjacent properties.
San Jose Creek
Channel Improvements - Estimated Cost: $2,825,000
This project consists of channel modifications to San Jose Creek downstream
of Hollister Avenue to increase channel capacity. The modifications will
primarily affect the top of the banks of the existing channel extending
approximately 3,500 feet downstream of Hollister Avenue. The end result
of this project is the removal of large portions of Old Town Goleta from
the 100-year flood zone.
Mission Creek -
Estimated Cost: $31,845,000
This project is located along Mission Creek from Canon Perdido St. to
Cabrillo Blvd. in the City of Santa Barbara. The Lower Mission Creek project
improves various channel locations with widenings and bridge replacements
in order to increase capacity. A park-like, open space environment is
incorporated in the design. Completion of this project will reduce flooding
and property damage adjacent to lower Mission Creek during large storm
events.
This is an Army Corps of Engineers (ACOE) flood control project. The ACOE
will fund up to 50% of the total project cost. The local cost share of
this project is being funded by the South Coast Flood Zone benefit assessment
revenues and by the City of Santa Barbara in accordance with a cost sharing
agreement.
Via Rueda Interceptor
Storm Drain - Estimated Cost: $965,000
This project consists of constructing a 36" diameter storm drain
above Via Rueda that will intercept storm flows from an unimproved portion
of the Vieja Drive Road Right of Way and convey those storm flows to Atascadero
Creek. The existing drainage facilities above the Via Rueda neighborhood
are inadequate, causing damage to the neighborhood as well as Flood Control
owned and maintained facilities constructed as part of the tract development.
Upon completion of this project, and by agreement between the Flood Control
District and the residents on Via Rueda, the District will quitclaim ownership
of the Flood Control facilities constructed with the tract to the property
owners, thus reducing the Districts maintenance obligations.
This project is being coordinated with the Puente Drive Bridge Replacement
project currently planned by the Transportation Division of the Public
Works Department. This coordination may result in combining a portion
of the storm drain work required for the bridge replacement with this
Flood Control project, potentially reducing costs for both projects.
West Side Storm
Drain Phase II - Estimated Cost: $4,870,000
This project is a cooperative project between the Flood Control District
and the City of Santa Barbara to construct the remaining phases of an
underground storm drain in the City of Santa Barbara. During frequent
rainfall events several of the streets and intersections in the City of
Santa Barbara's Westside community experience inundation and closures.
The Westside Storm Drain is a major storm water collection system designed
to alleviate this common flood problem.
The project was planned to be constructed in phases. The first phase of
this project was completed in 1997. Phase II will completed by the end
of the 2006-07 fiscal year. Phase III consists of the construction of
the upper reaches of the overall project. Construction of Phase III will
reduce the frequent inundation of roadways and adjacent properties. The
storm drain pipe sizes range from 30 inches to 66 inches in diameter.
San Ysidro Creek
Realignment - Estimated Cost: $320,000
In the mid 1950's when Highway 101 was constructed, Caltrans realigned
San Ysidro Creek resulting in abrupt bends forming in the creek immediately
upstream of North Jameson Lane. The condition has led to the accumulation
of debris at this location in significant storm events. This project will
remove the abrupt bends in the creek and promote a more hydraulically
efficient alignment. The completed North Jameson Lane Bridge Reconstruction
Project took into account this future alignment of the San Ysidro Creek.
Gobernador Debris
Basin - Estimated Cost: $700,000
This project will modify the Gobernador Debris Basin by replacing the
earthen embankment, grouted rock spillway and concrete low flow discharge
pipe with a natural bottom open channel and concrete restrictor walls.
The earthen embankment and low flow pipe are not conducive to fish passage.
This project is intended to improve the basins function by passing sediment
through the basin while retaining the more critical, larger, debris as
well as improve fish passage. Carpinteria Creek and its tributary Gobernador
Creek have been identified by fish studies as having prime potential to
re-establish habitat for steelhead trout. The National Marine Fisheries
Service has requested that the Flood Control District consider options
to modify the Gobernador Debris Basin to provide a more passable condition
for fish.
This project has received $88,000 in funding for preliminary engineering
and permitting efforts from a California Coastal Conservancy grant and
$156,805 in funding for construction and construction administration from
the CA Department of Fish and Game's Fisheries Restoration grant program.
Lower Arroyo Paredon
Basin - Estimated Cost: $3,525,000
This project consists of acquiring an easement over a portion of land
along Arroyo Paredon Creek north of Foothill Road. The easement area is
approximately 5 acres in the southeast corner of a 54.2 acre parcel. The
District would use this property to construct and maintain a debris basin.
This basin would be designed to capture the type of large debris that
typically comes down the creeks in this area during heavy rainfall events.
This type of debris has plugged the bridge on Foothill Road (Hwy 192)
in the past, with subsequent redirection of the creek, which has resulted
in flood damage to adjacent homes and downstream properties.
Padaro Lane Interceptor
- Estimated Cost: $1,110,000
This project is located adjacent to the coastline in western Carpinteria
Valley. The intent of this project is to alleviate some of the chronic
flooding that occurs between Arroyo Paredon Creek and the eastern terminus
of Padaro Lane. Proposed options are to intercept and divert storm water
away from the flood prone areas, construct a retention basin upstream
of Padaro Lane or improve existing drainage courses.
COMPLETED
CAPITAL PROJECTS
(Does not include storm repair projects.)
Santa Maria
Blosser Basin Bypass
Gate Box - Completed 2001
This project consisted of the construction of a gate box on the 48"
pipe that connects the Bradley Channel with the outlet channel from Blosser
Basin. This allows the diversion of water back into Blosser Basin.
Blosser Channel
Lining - Completed 2002
This project consisted of constructing concrete channel improvements along
Blosser Road from Alvin Ave. to Blosser Basin.
Getty/Kovar/Hobbs
Basin Interconnect -
Completed 2006
This project consisted
of the installation of a 24-inch storm drain pipe and slide gates to interconnect
the three basins. This provides our maintenance crews the ability to control
water levels in the three basins.
Kovar Basin Bypass
- Complete 1996
The project consisted of constructing a concrete structure containing
gate valves that will allow water coming from the Adams Park Basin to
be diverted during maintenance activities.
Prell Road Retention
Basin - Completed 2002
This project consisted of the construction of a large retention basin
on the east side of HWY 101 in Santa Maria at Prell Rd. in order to reduce
peak flows through the City of Santa Maria and associated flooding. A
new concrete box culvert was constructed under Hwy 101 from this basin.
Construction of this project utilized Hazard Mitigation Grant Funding
from the Federal Emergency Management Agency.
West Green Canyon
Storm Drain - Completed 2006
This project consisted of the construction of a storm drain in Santa Maria
running from a basin located at the intersection of A Street and Battles
Road north to Main Street and then west to the West Main Channel which
runs to the Santa Maria River.
Orcutt
Lakeview Storm
Drain - Completed
1996
This project consisted of the construction of a storm drain extension
in Lakeview Road from Hillview Road to Marvin Avenue.
Patterson Storm
Drain - Complete 1997
The project consisted of extending an existing 21-inch diameter storm
drain for a distance of approximately 500 feet between Orcutt Road and
Martin Avenue in the town of Orcutt, and constructing two catch basins
at the upstream terminus. The cost of this project was split 50/50 with
the Roads Division of Public Works.
Santa Ynez Valley
La Pita Place Drainage
Improvements - Completed 2002
This project consisted of constructing drainage improvements near La Pita
Place in Buellton in order to intercept and convey runoff to an existing
retention basin.
Lompoc
College-Walnut
Storm Drain - Completed
2003
This project consisted
of the construction of two storm drain extensions in the City of Lompoc.
One in College Avenue from A Street to D Street and one in Walnut Avenue
from 3rd Street to A Street.
Lompoc Valley
Santa Rosa Creek
Channel Stabilization Project -
Completed 2002
This project
consisted of the construction of an earthen embankment and channelization
of the creek.
South
Coast
Carpinteria Marsh
Project - Completed 2005
The project consisted of improvements to Santa Monica and Franklin channels
through the Carpinteria marsh; construction of earthen levees and floodwalls
to protect against flooding of adjacent developed properties.
Cravens Lane Storm
Drain - Completed
2002
This project
consisted of the construction of an underground storm drain and drop inlets
on Cravens Lane in the Carpinteria area. The storm drain intercepts a
portion of flows from Cravens Lane and direct them to the Franciscan Sediment
Basin.
El Encanto Debris
Basin -
Completed 2004
This project consisted
of improving storm water routing and debris removal by upgrading an existing
debris basin with retaining walls & an access ramp, located on Micheltorena
Street near California Avenue.
Encina Drain
- Completed 2001
This project
consisted of construction of a reinforced concrete box culvert under Calle
Real to Las Vegas Creek near the Calle Real Shopping Center.
Franciscan Culvert
Extension
- Completed 1999
This project
constructed a box culvert under Via Real and Highway 101 from an existing
basin on the north side of Via Real to an existing earthen channel located
south of the freeway.
Franciscan Sediment
Basin - Completed 2002
The project consisted of the construction a concrete lined channel and
a sediment basin upstream of the existing basin adjacent to Kim's Market.
Montecito Creek
Debris Basin Project
This project
was completed in September 2002 and won an APWA - Central Coast Chapter
award for an evironmental project between $2 - $10 million. For a photo
of the completed project, click here:
MontecitoDebris
Basin Photo
Old San Jose Creek
Improvements - Completed 2002
This project consisted of conveyance improvements to the existing natural
drainage channel from South Street to San Jose Creek channel. The project
involved grading, landscape revegetation, and the removal/enlarge of existing
bridge structures provide increased flood capacity of this natural creek
channel.
Serenidad Interceptor
Channel
- Completed 2003
This project
consisted of the construction of a 6-foot wide concrete interceptor channel
behind several homes in the vicinity of Serenidad Place in Goleta.
The new channel replaced an existing v-ditch that had proven inadequate
in prior flood events.
Venado Drive
- Completed 1998
This project
consisted of the construction of a storm drain in Venado Drive which drains
to an existing open channel to the south.
West Side Storm
Drain Phase I - Completed 1997
This project consisted
of the construction of a storm drain in west side area of Santa Barbara
to reduce street flooding. This was the first phase in a three phase project.
Contact us about this
web page:
Last
updated:
December 13, 2006
|