Schedule to TAC 6-25-02


Project Start Date: Mon 6/24/02
Project Finish Date: Thu 4/10/03

Who Does What

Resources and Assignments
StartFinishWork
Unassigned
Tue 6/25/02Thu 4/10/030 hrs
Subgroup Meeting (finalize work plan & schedule)
Tue 6/25/02Tue 6/25/020 hrs
TAC Meeting (present work plan & schedule)
Thu 7/11/02Thu 7/11/020 hrs
MJSWTG Meeting
Mon 7/22/02Mon 7/22/020 hrs
Task 1:Develop Guiding Principles
Tue 6/25/02Thu 8/1/020 hrs
Task 2: Develop Tech. Screening Parameters
Tue 6/25/02Thu 8/1/020 hrs
Task 3: Identify & Research Technologies
Tue 6/25/02Thu 8/1/020 hrs
Subgroup Meeting (finalize results of tasks 1-3)
Thu 8/1/02Thu 8/1/020 hrs
TAC Meeting (present results of tasks 1-3)
Thu 8/8/02Thu 8/8/020 hrs
MJSWTG Meeting (present results of tasks 1-3)
Mon 8/26/02Mon 8/26/020 hrs
Task 4: Screen Technologies
Thu 8/1/02Thu 9/5/020 hrs
Task 5: Develop Tech. Ranking Criteria
Thu 8/1/02Thu 9/5/020 hrs
Subgroup Meeting (finalize results of tasks 4 & 5)
Thu 9/5/02Thu 9/5/020 hrs
TAC Meeting (present results of tasks 4 & 5)
Thu 9/12/02Thu 9/12/020 hrs
MJSWTG Meeting (present results of tasks 4 & 5)
Mon 9/23/02Mon 9/23/020 hrs
Task 6: Rank Technologies
Thu 9/5/02Thu 11/7/020 hrs
Subgroup Meeting (update on task 6 progress)
Thu 10/3/02Thu 10/3/020 hrs
TAC Meeting (update on task 6 progress)
Thu 10/10/02Thu 10/10/020 hrs
MJSWTG Meeting (update on task 6 progress)
Mon 10/28/02Mon 10/28/020 hrs
Subgroup Meeting (finalize results of Task 6)
Thu 11/7/02Thu 11/7/020 hrs
TAC Meeting (present results of task 6)
Thu 11/14/02Thu 11/14/020 hrs
MJSWTG Meeting (present results of task 6)
Mon 11/25/02Mon 11/25/020 hrs
Task 7: Determine Institutional Arrangements
Thu 11/7/02Thu 12/5/020 hrs
Task 8: Identify Site Requirements
Thu 11/7/02Thu 12/5/020 hrs
Subgroup Meeting (finalize results of tasks 7 & 8)
Thu 12/5/02Thu 12/5/020 hrs
TAC Meeting (present results of tasks 7 & 8)
Thu 12/12/02Thu 12/12/020 hrs
Task 9: Conduct Community Forums
Thu 12/5/02Fri 12/20/020 hrs
TAC Meeting (update on task 9)
Thu 1/9/03Thu 1/9/030 hrs
MJSWTG (present results of tasks 7 & 8 and update on task 9)
Mon 1/27/03Mon 1/27/030 hrs
Task 10: Determine Feasible Technologies
Mon 1/6/03Thu 2/6/030 hrs
Subgroup Meeting (finalize results of task 10)
Thu 2/6/03Thu 2/6/030 hrs
TAC Meeting (present results of task 10)
Thu 2/13/03Thu 2/13/030 hrs
MJSWTG Meeting (present results of task 10)
Mon 2/24/03Mon 2/24/030 hrs
Task 11: Identify Jurisdictional Interest
Thu 2/6/03Thu 3/6/030 hrs
Subgroup Meeting (finalize results of task 11)
Thu 3/6/03Thu 3/6/030 hrs
TAC Meeting (present results of task 11)
Thu 3/13/03Thu 3/13/030 hrs
MJSWTG Meeting (present results of task 11)
Mon 3/24/03Mon 3/24/030 hrs
Task 12: Develop Final Report
Thu 3/6/03Thu 4/3/030 hrs
Subgroup Meeting (finalize report)
Thu 4/3/03Thu 4/3/030 hrs
TAC Meeting (present report)
Thu 4/10/03Thu 4/10/030 hrs