Project Start Date: Mon 6/24/02
Project Finish Date: Thu 4/10/03
Resources and Assignments | Start | Finish | Work |
|---|---|---|---|
Unassigned | Tue 6/25/02 | Thu 4/10/03 | 0 hrs |
Subgroup Meeting (finalize work plan & schedule) | Tue 6/25/02 | Tue 6/25/02 | 0 hrs |
TAC Meeting (present work plan & schedule) | Thu 7/11/02 | Thu 7/11/02 | 0 hrs |
MJSWTG Meeting | Mon 7/22/02 | Mon 7/22/02 | 0 hrs |
Task 1:Develop Guiding Principles | Tue 6/25/02 | Thu 8/1/02 | 0 hrs |
Task 2: Develop Tech. Screening Parameters | Tue 6/25/02 | Thu 8/1/02 | 0 hrs |
Task 3: Identify & Research Technologies | Tue 6/25/02 | Thu 8/1/02 | 0 hrs |
Subgroup Meeting (finalize results of tasks 1-3) | Thu 8/1/02 | Thu 8/1/02 | 0 hrs |
TAC Meeting (present results of tasks 1-3) | Thu 8/8/02 | Thu 8/8/02 | 0 hrs |
MJSWTG Meeting (present results of tasks 1-3) | Mon 8/26/02 | Mon 8/26/02 | 0 hrs |
Task 4: Screen Technologies | Thu 8/1/02 | Thu 9/5/02 | 0 hrs |
Task 5: Develop Tech. Ranking Criteria | Thu 8/1/02 | Thu 9/5/02 | 0 hrs |
Subgroup Meeting (finalize results of tasks 4 & 5) | Thu 9/5/02 | Thu 9/5/02 | 0 hrs |
TAC Meeting (present results of tasks 4 & 5) | Thu 9/12/02 | Thu 9/12/02 | 0 hrs |
MJSWTG Meeting (present results of tasks 4 & 5) | Mon 9/23/02 | Mon 9/23/02 | 0 hrs |
Task 6: Rank Technologies | Thu 9/5/02 | Thu 11/7/02 | 0 hrs |
Subgroup Meeting (update on task 6 progress) | Thu 10/3/02 | Thu 10/3/02 | 0 hrs |
TAC Meeting (update on task 6 progress) | Thu 10/10/02 | Thu 10/10/02 | 0 hrs |
MJSWTG Meeting (update on task 6 progress) | Mon 10/28/02 | Mon 10/28/02 | 0 hrs |
Subgroup Meeting (finalize results of Task 6) | Thu 11/7/02 | Thu 11/7/02 | 0 hrs |
TAC Meeting (present results of task 6) | Thu 11/14/02 | Thu 11/14/02 | 0 hrs |
MJSWTG Meeting (present results of task 6) | Mon 11/25/02 | Mon 11/25/02 | 0 hrs |
Task 7: Determine Institutional Arrangements | Thu 11/7/02 | Thu 12/5/02 | 0 hrs |
Task 8: Identify Site Requirements | Thu 11/7/02 | Thu 12/5/02 | 0 hrs |
Subgroup Meeting (finalize results of tasks 7 & 8) | Thu 12/5/02 | Thu 12/5/02 | 0 hrs |
TAC Meeting (present results of tasks 7 & 8) | Thu 12/12/02 | Thu 12/12/02 | 0 hrs |
Task 9: Conduct Community Forums | Thu 12/5/02 | Fri 12/20/02 | 0 hrs |
TAC Meeting (update on task 9) | Thu 1/9/03 | Thu 1/9/03 | 0 hrs |
MJSWTG (present results of tasks 7 & 8 and update on task 9) | Mon 1/27/03 | Mon 1/27/03 | 0 hrs |
Task 10: Determine Feasible Technologies | Mon 1/6/03 | Thu 2/6/03 | 0 hrs |
Subgroup Meeting (finalize results of task 10) | Thu 2/6/03 | Thu 2/6/03 | 0 hrs |
TAC Meeting (present results of task 10) | Thu 2/13/03 | Thu 2/13/03 | 0 hrs |
MJSWTG Meeting (present results of task 10) | Mon 2/24/03 | Mon 2/24/03 | 0 hrs |
Task 11: Identify Jurisdictional Interest | Thu 2/6/03 | Thu 3/6/03 | 0 hrs |
Subgroup Meeting (finalize results of task 11) | Thu 3/6/03 | Thu 3/6/03 | 0 hrs |
TAC Meeting (present results of task 11) | Thu 3/13/03 | Thu 3/13/03 | 0 hrs |
MJSWTG Meeting (present results of task 11) | Mon 3/24/03 | Mon 3/24/03 | 0 hrs |
Task 12: Develop Final Report | Thu 3/6/03 | Thu 4/3/03 | 0 hrs |
Subgroup Meeting (finalize report) | Thu 4/3/03 | Thu 4/3/03 | 0 hrs |
TAC Meeting (present report) | Thu 4/10/03 | Thu 4/10/03 | 0 hrs |