Project Title:Strauss Wind Energy Project
Case Number: 16CUP-00000-00031, 18CDP-00000-00001 18VAR-00000-00002
Project Location:Lompoc Area, Santa Barbara County
Assigned Staff and Division:

Kathy PfeiferEnergy, Minerals and Compliance Division

Status

What's New

The proposed Final Supplemental Environmental Impact Report (proposed FSEIR) is available. The proposed FSEIR has been revised based on all comments that were received during the public comment period and during the May 30, 2019 environmental hearing. Chapter 8 of the proposed FSEIR contains the public comments received and responses to those comments. Where appropriate, changes have been made to the Draft SEIR text in response to comments received, and have been incorporated into the proposed Final SEIR. The proposed FSEIR is contained in three documents: Volume I (Chapters 1-7), Volume II (Chapters 8and 9) and the Appendices. Please see the proposed Final SEIR links for the three documents below, including a link for the separate FSEIR chapters.

Planning Commission hearings have been set for Wednesday, November 20, 2019 and Friday, November 22, 2019. Both will be held at the County Planning Commission Hearing Room at 123 E. Anapamu Street in Santa Barbara. Please see the Planning Commission Notice link below.

Description

Stauss Wind, LLC, an affiliate of BayWa r.e. Wind, LLC, proposes to construct and operate a 102 megawatt (MW) wind energy project, the Strauss Wind Energy Project (SWEP), south of the City of Lompoc. The Project's Wind Site is located on 2,970 acres, consisting of 11 properties, and the Project's transmission line corridor would be located on 11 properties, starting at the Wind Site and running east and northeast to the City of Lompoc. The major components of the project include:

  • 30 wind turbine generators (WTGs) up to 492 feet tall;
  • a new 7.3-mile, 115-kilovolt (kV) transmission line to interconnect with the Pacific Gas and Electric (PG&E) electric grid;
  • an approximate 1-acre substation;
  • an approximate 1.4-acre switchyard;
  • an approximate 0.4-acre operations and maintenance building;
  • widening of existing onsite roads and construction of new roads; and
  • reconductor (replacing wires and poles) for 0.8 miles along PG&E's existing Manville 115-kV power line from the proposed switchyard to PG&E's Cabrillo substation in the City of Lompoc; and upgrades to the Cabrillo substation.

The SWEP's facilities, including all wind turbine generators (WTGs), the power line, and most access roads would be located in the Inland Area of the County and subject to the Santa Barbara County Land Use and Development Code (LUDC). Some grading of access roads would extend into the Coastal Zone and be subject to the Coastal Zoning Ordinance.

The SWEP application package includes applications for a Conditional Use Permit (CUP), a Variance for reduced property line setbacks for WTGs and modifications to setbacks of the WTGs from Vandenberg Air Force Base (VAFB) property, and a Coastal Development Permit (CDP) for grading of access roads within the Coastal Zone.

The Project site is the location of the previously proposed Lompoc Wind Energy Project (LWEP, 06CUP-00000-00009), which was approved by the County in 2009, but never constructed. A Final Environmental Impact Report (EIR) was prepared for the LWEP and certified by the County in February 2009 (County EIR No. 06EIR-00000-00004). The SWEP environmental review is a supplement to the LWEP EIR.

Timeline

Date Event Type
November 2019                                     Planning Commission Hearings are scheduled for November 20th and November 22nd.
October 31, 2019                                            Proposed Final SEIR available on County webpage.

 April 2019- June 2019                                                

 

Public review comment period for Draft SEIR. An environmental hearing was held on May 30, 2019 in Lompoc. 

July 2018 - April 2019                                   

 

Planning and Development had been working with their consultant, Aspen Environmental Group, to prepare a Supplement to the Lompoc Wind Energy Project Environmental Impact Report for SWEP.

July 2, 2018            

 

County Planning and Development submitted a Notice of Preparation to the State Clearing House, which initiated a 30-day public comment period.  A public scoping meeting was held on July 19, 2018.

April 6, 2018                   

 

County Planning and Development determined Strauss' application for a Conditional Use Permit to be complete.

December 21, 2016                

 

Strauss submitted a Conditional Use Permit application for the development of a utility-scale wind farm.


Documents

Planning Commission Hearing Notice

CEQA Materials

SWEP Final SEIR Transmittal

Proposed Final SWEP Supplemental EIR

       Proposed Final SEIR Volume I, II and Appendices

       Proposed Final SEIR Individual Chapters

Document by Section: Draft SWEP Supplemental EIR (Folder)

Full Document: Draft SWEP Supplemental EIR (PDF)

Notice of Availability - April 23, 2019

Scoping Meeting Notice

Notice of Preparation – July 19, 2018

LWEP Final EIR

Permit Application Materials

Permit Application Package