Click logo to go to County homepagePlanning and Development Energy Division  
 [  You Are Here:  County Home : Energy Home : Unocal ]
Site Search
Contact Us
 Energy Division Home
 Announcements
 Who We Are
 Oil & Gas Facilities Map

Projects
American Ethanol
Arco-Alegria
Arco-Dos Pueblos
Chevron-Aera
ConocoPhillips
E&B Resources
ExxonMobil
Gaviota Terminal
Abandonment

Greka
<empty> Hercules
Lompoc Wind Energy
Plains Pipeline, L.P.
PXP Pt. Arguello
PXP Tranquillion Ridge
<empty>& Pt. Pedernales
<empty> Southern Calif. Gas Storage
<empty>Enhancement Project
Sunset/ExxonMobil
Vahevala Project
Texaco
Unocal-Battles
Unocal-Pt Conception
Venoco Ellwood
Onshore Facility

Venoco Full Field
Development

<empty> Venoco Line 96 Project
Venoco SLC 421

 Permit Compliance
 Policies, Rulemaking
 Mitigation Programs
 Interagency Activities
 Information
 Links to Other Sites
 Website Page Links
end-section divider

In case of an oil
spill or gas release:

Call 911


Facility Operators
must also call:

Governor's Office of
Emergency Services
1-800-OILS-911


Energy Division
(805)886-7165


Click here for other
reporting requirements



Click here for normal
business hours contacts
 

Unocal Point Conception Decommissioning Project



What's New

  • Unocal began decommissioning the Cojo Marine Terminal and Point Conception facilities in June 2004. Most decommissioning activities were completed by Winter 2005, including:

    1. Removal of the nearshore portion of the Marine Terminal Loading Line

    2. Removal of the offshore portion of the Marine Terminal Loading Line

    3. Demolition of the Marine Terminal crude oil storage tank

    4. Demolition of the Butler building

    5. Removal of above ground storage tanks at Government Point

    6. Removal of above ground pipelines at Percos Beach

    7. Excavation and remediation of contaminated soil at Cojo Point

    8. Removal of pipe stanchions at Percos Beach

  • 9. Removal of exposed pipelines between the well site and Government Point

    • Soil remediation and removal of concrete and various piping at Government Point
    • Excavation and remediation of soil at the former Pt. Conception well site

    Now that deconstruction has been completed at all sites, long-term pipeline corridor and revegetation maintenance and monitoring is now underway.

  • As of January 2008, the following activities were completed:

    10. Revegetation and monitoring at former Pt. Conception well site and former Marine Terminal Site.

  • The following activities are still in progress:

    11. Groundwater monitoring and surveying for additional soil remediation necessary at Government Point

    12. Revegetation at Government Point and Percos Beach Dune Site*

* Revegetation progress toward performance goals at Percos Beach dune site is limited due to shifting dune conditions and the colonization of non-native plant species.

Long Term Site Maintenance and Monitoring

  • Revegetation areas shall be monitored regularly by Unocal and the County for a period of approximately 3 years until the performance criteria have been met. Maintenance shall consist of irrigation, weeding, replacement of erosion control devices and minimization of site disturbance from existing land uses. The County may recommend maintenance activities throughout the monitoring period.

  • Unocal has posted a performance bond with the County and is required to conduct a pipeline-monitoring program for a minimum of 25 years after project completion to determine if any of the remaining facilities become exposed in the future. If necessary, Unocal will then implement measures to restore all erosion-damaged areas. After 25 years the Santa Barbara County Planning Commission shall review the issue of facilities and equipment exposure and determine if the Unocal performance bond is still necessary.
  

Pre-Construction and Post-Construction Site Photos

In the fall of 2006, the Energy Division received pre- and post-construction photo documentation for the decommissioning of all three former Unocal Chevron facility sites at the Cojo Ranch. Shown below are “before and after” photographs of the three locations ( Cojo Bay, Government Point, and Point Conception) that were once used to accommodate oil and gas production facilities.

July 2003

View north of Government Point Production Facility
showing storage tanks and production well equipment

October 2006

View north of Government Point Production Facility
following abandonment of the facilities

View south of Point Conception Well Site showing the
former location of production wells and offshore pipelines

View south of Point Conception Well Site
following abandonment and revegetation efforts

View south of Cojo Marine Terminal onshore facility
depicting storage tank and associated support facilities;
the Marine Terminal loading line was located offshore to the South

View south of Cojo Marine Terminal onshore facility
following abandonment of the storage tank,
terminal line and associated facilities

 


Description

This site houses facilities in three locations (Cojo Bay, Government Point and Point Conception) that were once used to accommodate oil and gas production from offshore platforms (Harry and Herman) in the Point Conception field. The platforms have been removed and the existing marine terminal and production facilities are no longer active. These facilities were removed by the end of 2004. Since then, Unocal and its affiliates have worked to clean up and restore these sites to pre-commission standards.

Location

Gas and Facilities Map



Overhead View of Unocal's Cojo Facility

Cojo Bay Marine Terminal Site

Unocal's former Cojo Bay Marine Terminal site is located to the northeast of Point Conception, approximately 45 miles west of the City of Santa Barbara and 13 miles south of the City of Lompoc.

Government Point Production Facilities Site

Unocal's former Government Point Facilities site is located to the northwest of Point Conception, approximately 45 miles west of the City of Santa Barbara and 13 miles south of the City of Lompoc.

Point Conception Well Location

Unocal's former Point Conception well site is located to the northeast of the tip of Point Conception, immediately north of the Pt. Conception lighthouse facilities.


Overhead View of Unocal's Government Point and Point Conception Site

Cleanup Activities

Unocal's cleanup activities at Point Conception consist of a number of projects associated with the company's Cojo Bay marine terminal offshore loading line, Government Point production facility and various storage wells.

Cojo Bay Marine Terminal

  • The last barge loading at the Cojo Bay marine terminal occurred in 1987.
  • The terminal was placed under caretaker status in 1993.
  • The offshore mooring system was removed in the early 1990s.
  • Sections of offshore loading hoses were removed in late 1997.
  • The pipeline has been flushed with seawater to remove residual oil.

Government Point Production Facility and Wells

  • The Government Point production facility was last used in 1993 and placed under caretaker status that same year.
  • Four onsite oil wells were idled in 1993 and abandoned in 1999, which involved the cutting and capping of each well at a depth of 8 feet below ground surface and complete removal of the well cellars.
  • Four oil storage tanks have been emptied of remaining product and rinsed clean.

Past Activities

  • Phillips Petroleum Company constructed the Cojo Marine Terminal onshore facility in the early 1960s to accommodate the development of the State offshore tract PRC 2207 from Platform Harry. In the early 1970s, Phillips Petroleum abandoned and removed Platform Harry and all related onshore processing equipment connected to the marine terminal. Between Phillips' Platform Harry and Texaco's Platform Herman, 13 million barrels of oil/condensate and 747 billion cubic feet of natural gas were produced.
  • Union Oil Company constructed the Government Point production facility in the early 1970s. The site produced oil and gas from the Point Conception field (State Tidelands Lease PRC 2879). Production consisted of 21 million barrels of oil/condensate and 12 billion cubic feet of natural gas.
  • Unocal acquired the remaining Cojo Bay marine terminal facilities in 1973 in order to transport oil production from the Government Point facility to the marine terminal and onto oil tankers via an offshore loading line.
  • February 9, 2000, Unocal submitted an application to the Energy Division to decommission the facility at Cojo Bay and Government Point.
  • An Initial Study was conducted under the California Environmental Quality Act, which analyzed potential environmental impacts of the Phase II Abandonment Plan. Some impacts were found to be potentially significant, however mitigable. A mitigated Negative Declaration (02-ND-02) was prepared and circulated for review early in 2002.

 