Click logo to go to County homepagePlanning and Development Energy Division  
 [  You Are Here:  County Home : Energy Home : Lompoc Wind Energy Project  ]
Site Search
Contact Us
 Energy Division Home
 Announcements
 Who We Are
 Oil & Gas Facilities Map

Projects
American Ethanol
Arco-Alegria
Arco-Dos Pueblos
Chevron-Aera
<empty> ConocoPhillips
Cuyama Solar Array
E&B Resources
ExxonMobil
Gaviota Terminal
Abandonment

Greka
<empty> Hercules
Lompoc Wind Energy
Plains Pipeline, L.P.
PXP Pt. Arguello
PXP Tranquillion Ridge
<empty>& Pt. Pedernales
<empty> Southern Calif. Gas Storage
<empty>Enhancement Project
Texaco
Unocal-Battles
Unocal-Pt Conception
Venoco Ellwood
Onshore Facility

Venoco Full Field
Development

<empty> Venoco Line 96 Project
Venoco SLC 421

 Permit Compliance
 Policies, Rulemaking
 Mitigation Programs
 Interagency Activities
 Information
 Links to Other Sites
 Website Page Links
end-section divider

In case of an oil
spill or gas release:

Call 911


Facility Operators
must also call:

Governor's Office of
Emergency Services
1-800-OILS-911


Energy Division
(805)886-7165


Click here for other
reporting requirements



Click here for normal
business hours contacts
 

Lompoc Wind Energy Project

[Web page updated 07/12/11]


What's New

The project owner, Pacific Renewable Energy Generation (PREG), has indicated the company is considering possible modifications to the approved project, due to technical and economic factors. The County does not have details at this time. Any significant changes would require land use permitting and possibly further environmental review. As a result, project construction could be delayed beyond 2012. If an application is submitted for changes to the project, the information will be posted on this web page.

A Substantial Conformity Determination (SCD) to allow minor changes to the project description concerning installation of temporary and permanent meteorological towers was approved by P&D in October 2011. A follow-on Land Use Permit (LUP) for the changes was approved on December 12, 2011. The LUP approval may be appealed. Appeals must be submitted by December 22, 2011 to be considered. The public notice of the LUP approval is posted here.

For further information, please contact John Day at (805)568-2045.

Recent Information

The Lompoc Wind Energy Project continues to move forward toward construction. The project owner, Pacific Renewable Energy Generation (PREG), intends to finalize the project plans and obtain all required permits from state, federal, and local agencies by early 2012, so that construction can begin by spring or early summer 2012. Recent and upcoming activities are as follows:

  • The current plan for Phase I of project development is to erect thirty-seven 1.5 MW wind turbines (WTGs), to be located on the southern and central areas of the project site. Additional WTGs may be proposed at a later date. (The approved Conditional Use Permit allows up to a maximum of 65 WTGs on the site.)
  • The necessary geotechnical studies for access roads and wind turbines were completed in spring 2011.
  • Preliminary grading plans were recently reviewed by County P&D, Building & Safety Division.
  • PREG is currently working on applications for permits from the U.S. Fish & Wildlife Service, California Department of Fish and Game, and other agencies, as well as mitigation plans required by the County Conditional Use Permit.
  • PREG has applied to P&D for a Substantial Conformity Determination (SCD) to allow minor changes to the project description concerning installation of temporary and permanent meteorological towers. The application is currently in review, pending submittal of additional information. The changes are needed to allow additional wind measurements, to refine estimates of wind farm energy production, support project financing, and assess wind turbine performance. If the SCD is approved by the P&D Director, a follow-on Land Use Permit (LUP) will be approved. LUPs are publicly noticed and appealable.
  • The project will be presented for preliminary approval at the County Board of Architectural Review (Central Region) in a public hearing on July 15, 2011. A site visit open to the public will be held immediately before the hearing. The CBAR Agenda and associated staff memo are posted on the P&D website. The memo summarizes previous CBAR hearings for conceptual approval of the project.

What’s Next?

PREG is working to finalize detailed project plans and is working with County staff, California Department of Fish and Game, and other agencies to obtain permits and implement the required mitigation measures for environmental impacts of construction. The mitigation program to implement the conditions of the approved Conditional Use Permit is summarized in the Environmental Quality Assurance Plan (EQAP). PREG will submit detailed mitigation plans for review by P&D in the near future.

Once all required plans have been approved, P&D will review the project (Phase I) to ensure the detailed plans are consistent with the approved Conditional Use Permit and EIR. If found consistent, the Director of P&D would approve a Substantial Conformity Determination and P&D staff would issue an appealable Land Use Permit for Phase I of the project. P&D Building and Safety would then review and approve final grading and building plans, and construction could begin, subject to permits and approvals from other agencies. The EQAP document will serve as the basis for implementing and enforcing the mitigation program during and after construction. Construction is expected to begin by the summer of 2012.


Project Information

The project applicant is Pacific Renewable Energy Generation LLC (PREG), a subsidiary of Acciona Energy North America Corporation. PREG filed an application for a Major Conditional Use Permit on February 21, 2006, for a wind energy project, to be located on the wind-swept ridges south of Lompoc, adjacent to Vandenberg AFB. This will be the first major wind energy project in the County and will provide a significant source of alternative energy.

The project is situated entirely inland of the County’s Coastal Zone. The southern project boundary abuts the Coastal Zone boundary along the Vandenberg Air Force Base property line. The wind farm and power line will be located in the County’s 3rd Supervisorial District, except the final stretch of the power line will cross into the 4th District just south of the Lompoc City limit. The wind farm will consist of up to 65 wind turbines, each standing 389-397 feet high, including blades. Total electric generation capacity will be up to 97.5 megawatts, enough to power over 40,000 households. The power output will be sold to PG&E through a long-term power purchase agreement. A new power line will run from the project site to connect into an existing power line near PG&E’s Cabrillo Substation at the southwest corner of Lompoc. The wind turbines will be located on agriculturally-zoned grazing land (10 parcels; 2,950 acres), under 30-year lease agreements with the landowners. Existing gravel/dirt roads on the properties will be widened and some new roads constructed. Plans include an operations and maintenance building and an electrical substation on the project site.

The project may be constructed in up to three phases over seven years. The company currently plans to construct 37 turbines in the first project phase. These turbines will be located in the southern, central, and eastern areas of the project site. The remaining 28 turbines could be constructed in subsequent phases.

The project chronology is outlined below. It provides links to the EIR and other project documents.

 

Project Vicinity Map

 

 

Typical Landscape at Proposed Site

Typical Landscape at Proposed Project Site

Wind Farm in Similar Setting (Spain)

Wind Farm in Similar Setting (Spain)


Project Chronology

  • February 21, 2006 – Application filed for Major Conditional Use Permit.

  • May 24, 2006 – The Santa Barbara County Planning Commission held a Conceptual Review hearing on the project. Staff gave a brief overview , followed by a presentation by Michelle Conway of Acciona Wind Energy USA LLC. The staff’s report for the hearing includes the applicant’s project description and a site map. It is available at the Planning Commission web site.

    Public comments were heard from the Community Environmental Council, two City of Lompoc representatives, a project parcel owner, a project neighbor, and a Lompoc resident. Most speakers were supportive of the project, but identified a number of concerns, including: a) possible viewshed impacts from the Lompoc Valley; b) transmission line route; c) ground water resources; and d) impacts to Frick Springs, which is part of Lompoc’s water supply.

    The Commission took no action, as this was a conceptual review hearing. The Commissioners’ comments were generally favorable and supportive of the project proceeding to further review, while recognizing that potential environmental impacts have yet to be studied. Staff was urged to proceed with environmental review as soon as possible. The Commissioners’ comments during the hearing are summarized in the marked agenda.

  • June 1, 2006 – The permit application was found complete for processing.

  • June 2, 2006 – The project was reviewed by the County’s Agricultural Preserve Advisory Committee, as the project properties are under Agricultural Preserve Contracts. The Committee determined the project to be consistent with the Uniform Rules for Agricultural Preserves.

  • June 30, 2006 – A Notice of Preparation (NOP) was filed with the State Clearinghouse. The NOP initiated the Environmental Impact Report ( EIR) preparation process.

  • July 17, 2006 – An EIR Scoping Meeting was held at Lompoc City Council Chambers. Following a presentation by County staff, members of the public spoke about a number of potential adverse impacts of the project, including bird mortality from turbine operation and visual impacts from turbines and power lines. Several speakers described beneficial impacts.

  • August 15, 2006 – The contract for preparation of the EIR was approved by the Santa Barbara County Board of Supervisors. The consultant was selected cooperatively by the Project Applicant and the County.

  • July 17, 2007 – Draft Environmental Impact Environmental Report (EIR) released. Public comment period began. The entire Draft EIR is available for public review. Copies are available for review in Santa Barbara County Planning and Development (P&D) offices and several public libraries.

    Details are available on the Notice of Availability. CD copies may be obtained from our office.

    The Draft EIR identifies potential environmental impacts, mitigation measures, residual impacts and monitoring requirements. It documents that the Project could have significant short-term, construction impacts in the following areas: Visual Resources, Air Quality, Biological Resources, Cultural Resources, Fire Hazards/Emergency Services, Geology/Soils, Land Use, Noise, Paleontological Resources, Risk/Safety, Traffic/Circulation, and Water Resources. The Project could also have significant long-term, operational impacts to Visual Resources, Biological Resources, Fire Hazards/Emergency Services, Land Use, Noise, Risk/Safety, and Water Resources. Most of the environmental impacts would be reduced to less than significant through implementation of mitigation measures proposed by the Project Applicant and other measures proposed by the County.

    However, long-term operational impacts to Visual Resources and Biological Resources would remain significant and unavoidable. Significant visual impacts would include views of wind turbines from Jalama Beach County Park and of the proposed new power line along Highway 1 near Lompoc. The visual impacts of the power line could be reduced to less than significant by means of an Applicant-proposed alternative route. Potential for protected bird and bat species to be killed through collisions with wind turbine blades is found to be an unavoidable significant impact to Biological Resources.

    The Project’s significant and adverse effects should be considered in light of its beneficial effects. Beneficial effects include generation of 80 to 120 megawatts of alternative energy and support for continuing agricultural use of the project area.

  • August 6, 2007 – Public workshop on Draft EIR held in Lompoc.

  • August 30, 2007 – Public comment hearing on Draft EIR held in Lompoc. Comments were presented by eleven members of the public, organizations and agencies. While most comments were supportive of wind energy, concerns were raised about the adequacy of the draft EIR analysis in several issue areas, including of potential impacts to biological and visual resources, and effects on local residents.
  • September 4, 2007 – Close of public comment period. Late submittals were accepted from California Department of Fish and Game (CDFG) and U.S. Fish and Wildlife Service (USFWS). Twenty-nine written comments were received. Comments from the Audubon Society, Environmental Defense Center, CDFG and USFWS center on potential impacts to biological resources, particularly birds. Comments from California Department of Parks and Recreation include concerns about visual impacts on La Purisima Mission. Comments from PG&E and California Public Utilities Commission focus mainly on jurisdictional questions relating to the proposed power line from the project site to Lompoc. Other issue areas discussed in the comments include visual impacts, noise, archeological resources, traffic, impact on emergency services, and effects on local residents.

  • February 26, 2008 – New contract approved for Aspen Environmental Group to prepare the final EIR.

  • May 6 – 20, 2008 – Partial recirculation of Visual Resources section of draft EIR. The following documents are available: Notice of availability, Cover letter for recirculated section, Revised draft Aesthetic/Visual Resources section.

  • September 5, 2008 – Proposed Final EIR released. The following documents are available on this website:  Announcement of Availability; Proposed Final EIR.  (Note that the proposed final EIR and the final EIR are the same, except that the final EIR includes the section entitled “Modifications to FEIR Adopted Prior to Certification.)

  • September 30, 2008 – Planning Commission hearing. The hearing notice is posted on this site. The Planning Commission voted unanimously to certify the EIR and to approve the Conditional Use Permit and associated Variance. The Commission adopted modifications to the EIR, as provided in Attachment F to the staff report prepared for this hearing. The final permit conditions, including modifications made during the hearing, are provided in the Planning Commission Action Letter for the September 30 hearing. (Note that the EIR and permit conditions were further modified prior to final approval by the Board of Supervisors.) The public comment letters for this hearing and errata submitted before the hearing are posted at the Planning Commission website.

    The all-day hearing was well attended. During the public comment period 37 people spoke, most expressing strong support for the project. Significant adverse impacts of the project were raised and discussed. Property owners adjacent to the project site expressed concern about noise and visual impacts. Representatives of the environmental community, including Environmental Defense Center and Audubon Society, asked the Commission to consider more stringent protections, monitoring, and mitigation measures for birds and bats, which may be killed by the wind turbines. The Commission approved the project with minor modifications to the proposed bird mortality monitoring program and project decommissioning provisions. The CEQA findings of approval include a Statement of Overriding Considerations that project approval is warranted, notwithstanding that not all significant environmental impacts can be fully mitigated.

    The hearing was televised live and recorded by the County government TV station. DVD copies can be purchased from CSBTV. The hearing is posted in 6 parts on the CSBTV Archives site.

    Please follow the links to the staff report, proposed final conditions of approval, and Proposed Final EIR. The public comment letters for this hearing are posted at the Planning Commission website.

  • October 9-10, 2008 – Project Appeal. The Planning Commission's certification of the EIR and approval of the project was appealed to the County Board of Supervisors. Separate appeals were filed by the California Department of Fish and Game (CDFG) and George and Cheryl Bedford. The appeal hearings were docketed on the Board of Supervisors meeting agenda for December 16, 2008 (Departmental Agenda Items #8 and 9). Please see the Hearing Notice. At the December 16 Board meeting the project applicant and representatives of CDFG requested a continuance of the CDFG appeal hearing, because the parties expect to resolve the appeal issues through negotiations, which have been fostered by the County’s facilitated negotiation process. The Applicant also requested a continuance of the Bedford appeal hearing, to continue working to resolve issues raised by the Bedfords and also because the two appeals are interrelated. The Board voted to continue both hearings to February 10, 2009. Links to the Board Letters and other documents for these hearings are provided in the Agenda. The links are labeled File Reference No. 08-01014 and File Reference No. 08-010062, under Departmental Items 8 and 9, respectively. A video recording of the February 10 hearing is also posted on the Board’s website.

  • February 10, 2009 – The Final EIR was certified and the Conditional Permit approved by the Board of Supervisors. The approved permit conditions are included in the Board Action Letter.

  • June 30, 2009 – A zoning clearance was issued to increase the height of two existing meteorological (“met”) towers, as provided for in the EIR.

  • September 23, 2009 – A Land Use Permit was approved for minor modifications of the project description concerning scheduled removal of temporary met towers and the height, location, and number of permanent met towers. Approval was based on a Substantial Conformity Determination approved by the Director of P&D. An EIR addendum was adopted to reflect the changes, which will not create any additional environmental impacts. George and Cheryl Bedford appealed issuance of the Land Use Permit to the Planning Commission and then to the Board of Supervisors. The Board denied the appeal and granted final approval of the Land Use Permit (7/15/09). The appeal record is posted on the Board of Supervisors web site (see 7/15/09 agenda, Departmental Item 7, File Reference 09-00754).

  • March 24, 2010 – The Final Environmental Quality Assurance Plan (EQAP) submitted.

  • December 12, 2011 – A second Land Use Permit was approved for minor modifications of the project description concerning the number, locations, heights, and scheduled removal dates of temporary and permanent met towers. The public notice is posted here.

Planning and Development staff contact for this project is John Day (805)568-2045.


 

 

 

 
end of page content

Top